Petroleum Technology Institute (PTI), Warri, Power Upgrade Project

 

 

The PTI project was a power upgrade and replacement of obsolete high voltage panels within the institute.

The upgrade involved the installation of 6Nos. 500KVA 11/0.415kV distribution transformers with its associated compacted switchgear, feeder pillar and laying of 3x150mm2 11kV XLPE and the ground cable.

While the replacement involved the replacement of an 18- bay HV panel with its associated mimic control.